Pre-sheetrock meeting
Today afternoon I went to check on the house. I met with the foreman and we walked through the house to make sure everything is in order. We checked that the switches are in the roght places, there are enough plugs, there is no drain in the hallway, etc. They forgot to install a window, one of the bedrooms had no window what-so-ever. The important thing is that they’re taking care of everything and if all goes well they’re putting up the sheetrock Friday. This morning they also delivered the brick and they should start laying the brick early January. I asked for a couple more outlets and some more TV hookups, it seems like everything is in order. The builder said it’s about 75 more days from here so we should be moving in March!!!
Magyar
English
January 10th, 2006 at 10:15AM
puszil titeket az Eszti